What is it about?
Compares progressive design-build and CMGC, finding that the only difference is the allocation of design liability
Featured Image
Why is it important?
Provides a primer on progressive design-build for public agencies interested in using this project delivery method.
Perspectives
Negotiated contracts are not often used in the public transportation sector. The paper provides the basics to understand the strengths and weakness of these two project delivery methods.