What is it about?

Recommend practical solutions to prevent or mitigate the H2S gas destructive effects on human and machinery.

Featured Image

Why is it important?

To save lives.

Perspectives

The project average daily progress rate is 11m/day (330m/mo) for the first 15km of the tunnel was achieved. This advance rate was achieved with the aid of discussed provisions and in spite of continuous seepage of gaseous water and experiencing numerous interruptions in supply line and the derailing of the rolling stock.

Ghassem Jalilian Khave
Lar Consulting Engineers

Read the Original

This page is a summary of: TBM Tunnelling in Hydrogen Sulfide Gas Bearing Ground and its Solutions, Geotechnical and Geological Engineering, June 2013, Springer Science + Business Media,
DOI: 10.1007/s10706-013-9669-8.