Two approaches have been applied to find the total completion time of project, namely program evaluation and review technique (probabilistic PERT network) and binomial distribution cumulative density function (CDF)

Featured Image

Why is it important?

The final results show that the cumulative function method is more accurate than the traditional method (PERT) where the wasted time was decreased around 4 days. The total project completion time by using PERT is 33 days where it is 29 days by using the cumulative function method

Read the Original

This page is a summary of: Estimating the Optimum Completion Time of Project Using Binomial Distribution and Probabilistic PERT Network, January 2021, Springer Science + Business Media,
DOI: 10.1007/978-981-33-4389-4_57.